Month: November 2025

View All News Releases

THE DIRT: History of mining in Pine Creek

Historic ore bins and workings at a former Pine Creek mine.

While not as notable as Bunker Hill, Sunshine, or the Hecla Star, the mines of Pine Creek cannot go without proper recognition for their contributions to the Silver Valley. The Pine Creek Mining District, formerly known as the Yreka Mining District, is a smaller region within the larger Coeur d’Alene Mining District. Attributed to William Reineger in 1886, the discovery of Pine Creek’s lead-silver ore occurred two short years after its discovery in the larger district. Shortly after Reineger’s initial discovery, numerous other ore-rich areas were identified, and Pine Creek became home to over a dozen mines and several mills. 

Mineral bodies in the Pine Creek region were composed of a complex mixture of zinc, lead, silver, and antimony ores that early milling and processing methods struggled with. In the early years of milling, there was little to no attempt made to recover zinc due to inadequate processing technology. As such, little mining occurred until the onset of World War I, when high metal prices and demand stimulated development and resulted in considerable production. The Pine Creek district faced multiple issues when attempting to install a rail line to transport ore. In 1917, after several miles of track were completed, a washout severely damaged portions, and the work was discontinued. This inability to complete a branch line in the district slowed production after the war. 

Direct discharge disposal practices, legally used throughout the larger district, were also implemented in Pine Creek. Massive quantities of tailings were discarded throughout the drainage during this time. With only inefficient recovery methods available, this disposal practice introduced metal-laden waste products into Pine Creek and its tributaries. These sediments contained lead and other metals that were hazardous to humans, the environment, and aquatic species such as cutthroat and bull trout. These activities also increased the sediment loading within the creek bed and widened the stream channel in many stretches.

With the invention of the selective flotation concentration method in the 1920s, metal recovery rates greatly improved. This allowed mills to easily separate individual metals, creating a new market for zinc. The Sullivan Mining Company, owned by Hecla and Bunker Hill, constructed the very first electrolytic zinc plant in the United States to capitalize on this new process. The new zinc plant was constructed in Government Gulch just south of Bunker Hill’s lead smelter. Bunker Hill also remodeled its Sweeny Mill to handle custom ores from the Pine Creek mines. A 3.5-mile tramway was constructed to transport Pine Creek ores. This tramway ran from the Sidney Mine, located at the head of Red Cloud Creek, northeast over the mountain to the Sweeny Mill at the bottom of Government Gulch. 

Higher efficiency recovery rates and the construction of the zinc plant contributed to a period of sustained mining activity between 1924 and 1930. Unfortunately, the mines were not immune to the ill effects of the Great Depression, which led to reduced operations or the complete shuttering of many mines. Recovery took time, but the passage of the federal Silver Purchase Act in 1934 encouraged mines that produced silver to reopen. At the end of the decade, rumors of war boosted metal prices even more, and local mills began processing ore that had been stockpiled during the depression. 

With the onset of World War II, the demand for lead, zinc, and antimony grew, but many mine and mill workers joined the armed services, thereby creating a labor shortage across the industry. As a result, production from the Pine Creek mines never again reached the levels they had during World War I. In the 1950s, new federal programs instituted by the Department of the Interior encouraged exploration, development, and mining, benefiting many area mines, but these programs were short lived. By the end of the 1960s, a combination of factors, including declining metal prices, higher operating costs, and dwindling reserves, led to the permanent closure of most of the Pine Creek mines and mills. Smaller operations and exploration work continued into the 1980s, but by this period in time the mining rush of Pine Creek was all but over. 

The Dirt is a series of informative articles focused on all aspects of cleanup efforts associated with the Bunker Hill Superfund Site. Our goal is to promote community awareness of contamination issues, to provide tools for protecting public health, and to keep the community informed of current and future cleanup projects. The Dirt is a group of committed and local experts from multiple agencies, including the Basin Environmental Improvement Project Commission, Panhandle Health District, Shoshone County, Silver Valley Economic Development Corporation, and the Idaho Department of Environmental Quality. 

View All News Releases

THE DIRT: Canyon Creek’s path to cleanup

Cleanup work being performed at the Star Mine along Canyon Creek

Significant progress has been made in Canyon Creek over the past several years, with multiple major remediation projects recently completed or underway. These efforts are aimed at removing contaminated material, remediating and reconstructing stream channels to provide a clean habitat. Work in Canyon Creek has been prioritized to reduce risk for residents living in close proximity to mine-impacted materials with high concentration of metals such as lead.

Cleanup began at the Star Project in 2023 and is well into its three-year construction plan. In 2025 alone, crews excavated roughly 48,000 cubic yards (CY) of waste material, which is about 4,800 dump truck loads moving 10 CY per load. To reclaim the area, approximately 47,000 CY of clean fill and vegetative cover soils will be placed back into the site. In addition, about 800 linear feet (LF) of stream will be reconstructed this year. Over the project’s duration, waste excavation will total around 150,000 CY, with nearly 2,800 LF of stream reconstruction completed.

Another major effort, the Tamarack No. 7 Project, has a cleanup scheduled from 2025 to 2026. Work in 2025 included excavation of approximately 109,000 CY of waste and the remediation of about 1,900 LF of stream channel. By project completion in 2026, it is projected that about 165,000 CY of waste will be removed and 3,100 LF of stream restored.

Earlier efforts laid important groundwork for this recent progress. From 2019 through 2022, the SVNRT Remediation Project successfully removed nearly 600,000 CY of waste material. While no direct stream remediation was conducted under this project, it moved mine waste into an appropriately constructed repository and added substantial disposal capacity for future cleanup work. The Canyon Complex Repository (CCR) now provides about 1.8 million CY of total capacity to support ongoing and upcoming cleanup activities.

Looking forward, several additional projects are planned to maintain momentum. These include work on the Flynn Mine/Black Bear Fraction, Canyon Creek Garbage Dump, Standard Mammoth Reach, Frisco Reach, Gem Complex, Lower Canyon Creek Riparian Area, and the Standard Mammoth Millsite. These sites stretch from just above the Star to the bottom of Canyon Creek.

Overall, these projects represent a significant investment in the health and resilience of Canyon Creek. The pace of work achieved over the last few years is expected to continue in the coming years. These projects strengthen Canyon Creek’s health and resilience and will continue driving measurable environmental progress in the area.

The Dirt is a series of informative articles focused on all aspects of cleanup efforts associated with the Bunker Hill Superfund Site. Our goal is to promote community awareness of contamination issues, to provide tools for protecting public health, and to keep the community informed of current and future cleanup projects. The Dirt is a group of committed and local experts from multiple agencies, including the Basin Environmental Improvement Project Commission, Panhandle Health District, Shoshone County, Silver Valley Economic Development Corporation, and the Idaho Department of Environmental Quality.