View All News Releases

THE DIRT: The history of roads in the Silver Valley Pt. 2

Image showing sewer project requiring local road to be torn up. Various colors are seen in the soil, showing the different types of mine waste present.

As noted in part one of this series, the Silver Valley’s mining legacy runs deeper than its mountains—it is built right into the roads beneath our feet. For decades, mine waste was routinely used to build and maintain local roadways, rights-of-way, and driveways. Though this practice is long behind us, its impact can still surface today, especially for the road crews, utility workers, and contractors who continue to work in these areas. 

Due to the widespread depth and distribution of contamination throughout the Bunker Hill Superfund site, complete removal of these waste materials was not economically feasible, nor logistically possible. As such, only partial removals of contaminated materials could be completed. Remediation depths vary, but most clean barriers will be either 6 or 12 inches deep, creating a clean protective layer over the remaining contaminated waste. 

Roadbeds and rights-of-way are common places to run underground utilities such as fiber, gas, water, and sewer. This means most of the utility lines found within or adjacent to roadbeds throughout the Silver Valley were placed in contaminated materials. When utility, roadway, or ditch maintenance is needed, our local contractors are faced with the task of performing necessary repairs while also maintaining and restoring any remediated barriers they may encounter. This can be a big challenge, taking more time and effort than working in unremediated areas. To ensure this work is done properly and safely, contractors are encouraged to take the ICP class before working within the Superfund site. 

Crews must protect remediated barriers by excavating and separating the clean barrier materials, then separating and isolating any of the deeper contaminated materials. Mishandling of contaminated materials during excavation can result in recontamination of clean areas and expose children and those near construction sites to lead and other metal contaminants. The responsible handling and disposal of these materials ensures that public health and the safety of the surrounding environment are protected. When all work is complete, contractors must ensure that the remediated barriers are restored to their original condition. While this process adds a layer of complexity to their everyday tasks, our local construction crews have mastered the methods needed to complete their work while protecting the remediation barriers that prevent accidental exposure to the contaminants that remain in our area. We thank them for their hard work and continued efforts to work safely and protect us all! 

The Dirt is a series of informative articles focused on all aspects of cleanup efforts associated with the Bunker Hill Superfund Site. Our goal is to promote community awareness of contamination issues, to provide tools for protecting public health, and to keep the community informed of current and future cleanup projects. The Dirt is a group of committed and local experts from multiple agencies, including the Basin Environmental Improvement Project Commission, Panhandle Health District, Shoshone County, Silver Valley Economic Development Corporation, and the Idaho Department of Environmental Quality.